Liberty Electric Project
Client: Duke/Fluor Daniel (EPC Contractor) for Liberty Electric Power,
LLC, (an affiliate of Reliant Resources, Inc.).
Location: Eddystone, Pennsylvania, USA
Project Description:
550 MW Combined-Cycle Electric Generation Facility. Major equipment
includes two General Electric model PG-7241 FA combustion turbine
generators, two Aalborg heat recovery steam generators (HRSGs) with
integral duct firing, and one Toshiba condensing steam turbine
generator. Dry low-NOx combustors and a selective catalytic reduction
system are used in this facility for turbine exhaust emission control.
The facility uses evaporative coolers for inlet air cooling and power
augmentation. The project was completed in March of 2002.
Scope:
Noise Control Engineering: (a) Permitting assistance, (b) Design
engineering, (c) Procurement support, (d) Compliance verification
survey, and (e) Post-commissioning noise reduction troubleshooting.
Regulatory Involvement and Environmental Documentation:
Provided initial plant noise emissions predictions, associated community
impact assessment, and engineering design basis noise study to project
for use in discussions with local authorities.
Noise Control Services:
The Liberty Project, located in Eddystone, Pennsylvania (just outside of
Philadelphia), is a brownfield project located at the previous Baldwin
Locomotive Facility. Noise requirements were complicated by the
combination of several local jurisdictions, as well as varying adjacent
land uses, including industrial, commercial, and residential zones. As a
sub-contractor to the turnkey engineering contractor, Duke/Fluor Daniel,
AAC staff was involved with the noise control aspects on this 550 MW
combined-cycle electric generation facility from the proposal phase
through detailed design and into post-commissioning retrofitting.
The noise control engineering design basis was established via
predictive computer modeling before any equipment items were ordered or
plant layouts were finalized. Noise control limits were assigned to all
major noise sources and the main turbine building’s acoustical features
were integrated into the overall plant design to ensure meeting the
project requirements. Following start-up, AAC engineers made scores of
measurements within the plant, at the facility boundary, and at adjacent
community receptor locations to verify and document noise compliance
during partial- and full-load operations. Later, after some concerns
from the owner and local citizens about start-up noise during merchant
plant operations, AAC again mobilized considerable resources and
instrumentation to the site and conducted extensive on-site
troubleshooting of steam vents, by-pass valves, steam lines, and drum
resonances. Troubleshooting measurements involved taking noise level
data at a dozen sampling locations simultaneously to assess the temporal
changes in noise emissions throughout the start-up process and to
pin-point the worst offenders. Noise control methodologies were
recommended and implemented by the plant to reduce start-up noise
emissions to acceptable levels.
|
 |