Newington Energy Facility
Client: Duke/Fluor Daniel (EPC Contractor) for ConEd Development
Location: Newington, New Hampshire, USA
Project Description:
525 MW Combined-Cycle Electric Generation Facility. Major equipment
includes two General Electric (GE) model PG7241 FA combustion turbine
generators, two Foster Wheeler heat recovery steam generators (HRSGs)
with integral duct firing, and one GE D11 condensing steam turbine
generator. Dry, low-NOx combustors and a selective catalytic reduction
system are used in this facility for turbine exhaust emission control.
The facility uses evaporative coolers for inlet air cooling and power
augmentation. Overall plant cooling is provided by a 10-cell wet cooling
tower from Marley Cooling. The project was completed in fall of 2002.
Scope:
Noise Control Engineering: (a) Permitting assistance, (b) Design
engineering, (c) Procurement support, (d) Compliance verification
survey, and (e) Post-commissioning noise reduction troubleshooting.
Regulatory Involvement and Environmental Documentation:
Provided initial plant noise emissions predictions, associated community
impact assessment, and engineering design basis noise study to the
project for its use in discussions with local and state authorities.
Noise Control Services:
The Newington Project, located in Newington, New Hampshire (just west of
Portsmouth), is a combined-cycle electric generation facility located in
a mostly commercial/industrial near the Piscataqua River. Due to a
smattering of residential properties in all directions, most within
1,400 feet of the plant (the closest being around 850 feet away), noise
was a concern from the outset of the project’s development. Noise
requirements were detailed, complicated, and restrictive – given the
nearby residential land uses – involving absolute noise level limits,
restrictions on incremental increases above the pre-plant ambient, tonal
limits, and a criterion for community responses to industrial noise.
AAC staff members were involved with the noise control aspects on this
project over several years; from the proposal phase through detailed
design and into compliance verification and post-commissioning
troubleshooting.
Predictive computer modeling helped establish the noise control
engineering design basis, as well as the noise control emissions limits
for all major noise sources. This modeling investigation was key to
defining the main turbine building’s acoustical features as well as
special-design characteristics for many potentially noisy mechanical and
electrical equipment items. During and after start-up, AAC engineers
measured noise levels within the plant and at adjacent community
receptor locations to document noise emissions from specific equipment,
as well as the overall plant. Items that were not performing,
acoustically, according to the purchase agreement were identified and
vendor modifications were initiated. Later, AAC engineers made detailed
verification measurements, in parallel with noise consultants
representing the city, to confirm facility compliance and/or identify
additional noise problems. Spectral data pointed to particular
motor-drive systems as still not meeting the design specification and,
therefore, needing mitigation treatments. AAC worked with the
contractor’s staff and the equipment vendor to enclose the motors for
acceptable noise performance and plant compliance.
|
 |